Turntable foundation cement work
Marty, Bruce, Bill, and Kevin started the 27.5 60# bags of cement before it got warm.
Lots of work was done in the field for switch stands.
Steve hosted a meeting on place name signage after lunch.
In the shop Ken & Carl continue to be frustrated by the recalcitrant press brake.
Mike’s team assembled a C16 frame for the roundhouse in the shop.
Photos - click on images for text descriptions and large images